If a contract provides for a retention of 5% of a $135,000 total job price, how much may the owner withhold?

Prepare for the California Landscaping Contractor Exam. Study using our resources with multiple-choice questions and detailed explanations. Get exam-ready with confidence!

Multiple Choice

If a contract provides for a retention of 5% of a $135,000 total job price, how much may the owner withhold?

Explanation:
Retention is the portion of the contract price held back by the owner as security that the work will be completed properly. When the contract specifies 5% retention, you apply that percentage to the total job price to find the amount that can be withheld. For a $135,000 job, 5% is 0.05 × 135,000 = 6,750. So the owner may withhold 6,750 under this clause. (Retention is typically released later, after completion and meeting any required conditions, but the amount currently withheld is determined by the percentage applied to the total price.)

Retention is the portion of the contract price held back by the owner as security that the work will be completed properly. When the contract specifies 5% retention, you apply that percentage to the total job price to find the amount that can be withheld. For a $135,000 job, 5% is 0.05 × 135,000 = 6,750. So the owner may withhold 6,750 under this clause. (Retention is typically released later, after completion and meeting any required conditions, but the amount currently withheld is determined by the percentage applied to the total price.)

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy