How many days does a prime contractor have to record a Claim of Lien after a Notice of Completion has been recorded?

Prepare for the California Landscaping Contractor Exam. Study using our resources with multiple-choice questions and detailed explanations. Get exam-ready with confidence!

Multiple Choice

How many days does a prime contractor have to record a Claim of Lien after a Notice of Completion has been recorded?

Explanation:
After a Notice of Completion is recorded, the window to file a Claim of Lien tightens to 60 days. This rule exists because the notice signals the project is wrapping up, and it gives all parties a shorter, final period to secure payment with a lien. For a prime contractor, that means you must record the lien within 60 days of the Notice of Completion being recorded; missing that window can jeopardize the lien claim for that project. So, 60 days is the timeframe to rely on when a completion notice is on file. The other numbers don’t apply in this scenario: the standard period without a completion notice is longer (often 90 days after last labor or materials), and 120 days isn’t the applicable deadline after a Notice of Completion.

After a Notice of Completion is recorded, the window to file a Claim of Lien tightens to 60 days. This rule exists because the notice signals the project is wrapping up, and it gives all parties a shorter, final period to secure payment with a lien. For a prime contractor, that means you must record the lien within 60 days of the Notice of Completion being recorded; missing that window can jeopardize the lien claim for that project.

So, 60 days is the timeframe to rely on when a completion notice is on file. The other numbers don’t apply in this scenario: the standard period without a completion notice is longer (often 90 days after last labor or materials), and 120 days isn’t the applicable deadline after a Notice of Completion.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy